If 10 men can complete a job in 6 hours, how many total man-hours are needed to finish the job?

Study for the USTET Exam. Enhance your mental ability skills with flashcards and multiple-choice questions, complete with hints and explanations. Ace your exam!

To determine the total man-hours required to complete the job, we can start by calculating the total work performed by the men involved. Since 10 men can finish the job in 6 hours, we do the multiplication of the number of men by the number of hours they work:

Total man-hours = Number of Men × Hours Worked

Total man-hours = 10 men × 6 hours = 60 man-hours.

This means that collectively, the team of 10 men contributes 60 hours of work towards completing the job, which indicates how much total effort is needed to finish the job. Each man contributes to this work, and since they are working together, their combined efforts effectively result in a total of 60 man-hours required. Hence, the calculation confirms the total amount needed for the job completion.

It's important to recognize that the answer provided initially was not the correct reflection of this calculation, which emphasizes the understanding of how to measure work in man-hours accurately.